Guwahati has been suffering from urban floods caused by water logging after heavy rainfall in its catchment area. The situations aggravates with the inflow of Meghalaya storm water that passes through the drainage system of Guwahati city and ultimately percolate to Brahmaputra either by gravity flow or mechanically with the help of pumping system. Although steps are being taken to mitigate the effects of and ultimately thwart the occurrence of such floods; what is urgently required is a comprehensive response mechanism which takes into account all emergency processes under one umbrella, and all stake-holders under one control. In this regard, it may be cited that the experience the world over is that a prompt, well-coordinated andeffective response to any disaster not only minimizesloss of life and property but also facilitates early recovery.
National Disaster Management Agency has developed and adopted the Incident Response System (IRS) for disaster management – a novel methodology based on the Incident Command System (ICS) of the United States.
S. N. | Name of Scheme | Est. Amt (Rs in Lakhs) |
GMDA Machinery engaged, if any |
---|---|---|---|
1 | Development of Silsako Beel to increase its storm water retention capacity with the help of fleet of machineries for the year 2017-18 |
125.00 | 1. Amphibian Dredger, Watermaster.- 1 Nos 2. Amphibious Excavator, JS-205 - 1 Nos 3. Speed Boat - 3 Nos |
2 | Desiltation and cleaning of NBCC Drain for the year 2017-18 |
36.76 | 1. Barge Mounted Excavators, Ex-70 – 2 Nos |
3. | Desiltation and cleaning of Bondajan Beel by deploying of fleet of machineries for the year 2017-18 |
36.00 | 1.Barge Mounted Excavators, Ex-70 – 1 No |
4. | Dredging for de-siltation and cleaning & re-grading of Pamohi Channel and NH-37 Drain with the help of fleet of machineries for the year 2017-18 |
97.77 | 1. Amphibian Dredger, Big Float.- 1 No. 2.Amphibious Excavator, JS-205 – 1 No. 3. Barge Mounted Excavators, Ex-70 – 1 No |
5. | Desiltation & Cleaning of Borsola Beel with the help of fleet of machineries for the year 2017-18 |
32.03 | Barge Mounted Excavators, P-71 – 1 No (The excavator taken on hire Charged) |
S. N. | Name of Work | Estimated Amount (Rs in Lakhs) |
Status |
---|---|---|---|
1 | Construction of Noonmati Basin Drain | 2014.00 (Revised) | Completed |
2 | Raising of existing guard wall along both sides of Bharalu River from Jonali to G.S. Road |
53.79 | Work Progress 90% |
3. | Extension of Noonmati Basin Drain up to ASIDC point to Bamunimaidam |
1969.86 | Work Progress 50% |
4. | Construction of Concrete Silt trap with silt removal arrangement as a pilot project at river Bharalu Near ASTC Central Depot. |
228.32 | Tender process is completed. |
5. | Construction of RCC box storm water drain from F.A.Ahmed Road side drain to Silsako water body with cross culvert. |
199.83 | NIT floated |
6. | Construction of box drain for straightening of Juripar Channel last left hand side bend and construction of link drain from F.A.Ahmed road side drain to Silsako Beel with cross culvert (Phase-I). |
95.66 | NIT floated |
Borsola Beel before restoration |
Borsola Beel after restoration |